Tomorrow, on May 14 starting at 8 a.m., a contractor with be at four locations along Third Avenue in downtown Strathmore from Lakeside Boulevard to Second Street to complete paving and excavation. The town advises that crews may take up a few parking stalls while each location is assessed.

During the assessment, small squares will be jack hammered and excavated to remove hazards identified by the Town of Strathmore.

The excavated area will be compacted and repaved. It’s expected the work will be complete before the end of the day.